Recommended procedures: Replacement of item within regularly scheduled maintenance program; new bracing with a similar or a high grade steel quality
Leitung:
Musterort
Systeme:
001/002
Mastnummer:
22
Baujahr:
1975
Nennspannung:
380 kV
Letzte Inspektion:
19.05.2021
IR-Auffälligkeiten:
0
Weitere Auffälligkeiten:
4
Zustandsbewertung:
2
Route planning
X go back
Name of Overhead line:
Musterort
Number of Systems:
001/002
Number of Pylon:
22
Year of manufacture:
1975
nominal voltage:
380 kV
Date of last Inspection:
19.05.2021
IR-Conspicuousness:
0
Other Conspicuousness:
4
Condition (assessment):
2
Glass cap separation
X go back
Recommended procedures: Insulator need to be replaced within a short time
Route planning
X go back
Digital monitoring of substations: Applications
X go back
Short circuit risk due to bird's nest
X go back
Recommended procedures: Immediate action required; all items need to be removed
Conductor damage at bundle spacer
X go back
Recommended procedures: Immediate action required. Conductor needs to be repaired; Spacer needs to be replaced
Distorted vibration damper
X go back
Recommended procedures: Damper needs to be replaced within a short time; conductor needs to be inspected for any damages
Hot spot on midspan joint
X go back
Recommended procedures: Joint needs to be replaced on bypassed depending on severity; conductor need to be replaced on reinforced; joints need to be inspected, visually and electrically
Profile map/plan
X go back
Line Inspection
X go back
Schneisenmanagement
X go back
Inhalt?
X go back
Hot spot on midspan joint
X go back
Recommended procedures: Joint needs to be replaced on bypassed depending on severity; conductor needs to be replaced on reinforced; joints need to be inspected, visually and electrically